In a landmark judgment delivered by the Hon’ble Bombay High Court on February 24, 2026 (Nusli Neville Wadia v. Ijimima – Imitation Jewellery Market Co-operative Society & Ors., Writ Petition No. 14690 of 2022 and connected petitions), the High Court addressed crucial questions surrounding promoter obligations, phased layout developments, and statutory rights under the Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963 (MOFA).
The High Court affirmed the Order of Unilateral Deemed Conveyance passed by the Competent Authority under Section 11 of MOFA, ruling that statutory obligations imposed on promoters under MOFA override inconsistent contractual clauses, and that the non-completion of subsequent phases in a multi-building layout cannot indefinitely freeze or postpone the conveyance of land for completed structures.
Land and Development Framework: The petitioner, Nusli Neville Wadia (as Administrator of the Estate of Late E.F. Dinshaw), owned a larger land parcel admeasuring 89,056 sq. meters at Malad (West), Mumbai. In 1995, development agreements were executed appointing project coordinators and developers (Ivory Properties and subsequently Radhakrishna Properties Pvt. Ltd.) for phased development.
The Project and Unit Sales: In 2003, a layout named "Raheja Metroplex" comprising Building Nos. 1 to 10 was sanctioned by the Municipal Corporation of Greater Mumbai (MCGM). Units in Building No. 4 were sold under MOFA-registered agreements to members of the Imitation Jewellery Manufacturers’ Association.
Handover and Delay: Building No. 4 was completed in 2005, an Occupation Certificate was issued, and unit purchasers took possession. In May 2009, the Ijimima – Imitation Jewellery Market Co-operative Society was formally incorporated. However, for nearly two decades after 2005, no further development took place regarding the remaining planned buildings (Building Nos. 1–3 and 5–10).
Deemed Conveyance Order: Following unanswered demands for conveyance, the Society applied under Section 11 of MOFA. On August 29, 2022, the Competent Authority granted Unilateral Deemed Conveyance in favor of the Society for a proportionate land share (16,747.19 sq. meters plus 22% recreational ground area). This order was challenged in the High Court by the landowner and developers through writ petitions.
The petitioners primarily raised three main lines of argument:
Leasehold vs. Freehold Ownership: The petitioners argued that foundational agreements (including early MOUs and draft clauses) contemplated the grant of a long-term lease (e.g., 999 years) rather than absolute freehold conveyance, and that the Competent Authority could not grant a title higher than what was contractually envisaged.
Indefinite Postponement via Phased Layout: It was contended that because the larger layout envisaged 10 buildings and an ultimate transfer to an apex body upon full completion, individual societies could not demand conveyance until the entire layout was fully developed.
Procedural Defects and Natural Justice: One of the co-promoters claimed lack of proper service under Rule 13(2) of the applicable rules due to notices being sent to an old registered office address.
The judgment reinforces established principles governing real estate jurisprudence and statutory welfare enactments in Maharashtra:
Under Section 11 of MOFA, promoters are under a statutory mandate to complete their obligations regarding the transfer of title. The court reaffirmed that contractual terms attempting to restrict or indefinitely delay conveyance in a manner inconsistent with MOFA provisions are unenforceable. Statutory protections designed to prevent buyer exploitation take precedence over restrictive covenants.
Where a promoter fails to execute subsequent phases of a multi-building layout over an extended period (here, nearly 20 years), the promoter cannot use the incomplete status of the remaining layout as a shield to deny or postpone deemed conveyance to unit owners of completed buildings who have fully paid their consideration and taken possession.
The Competent Authority under Section 11 acts within its jurisdiction when granting proportionate undivided share in land and common areas calculated on the basis of consumed floor space index (FSI), plinth area, and sanctioned layout plans, particularly in line with applicable Government Resolutions (such as the GR dated June 22, 2018).
Relief for Stalled Co-operative Societies: This judgment provides substantial clarity and comfort to thousands of registered co-operative societies across Maharashtra operating within partially completed or stagnant multi-building layouts where developers have stopped further construction.
Precedent on Unilateral Deemed Conveyance: It underscores that the right to seek deemed conveyance under MOFA cannot be rendered illusory by inserting restrictive lease clauses or relying on incomplete layout arguments to maintain perpetual control over the land.